Groundwork Register
EIA-860M file 2026-07

Planned power projects in Millard, UT

5 planned generator projects are listed for Millard County, UT in the EIA-860M inventory, with a combined stated nameplate of 2074 MW. By type: Solar 3 ยท Battery storage 2.

Planned generators (EIA-860M)

ProjectTypeCapacityStatus (as reported)Planned onlineSource
Notch Peak Solar LLC
Notch Peak Solar LLC
Solar Photovoltaic324 MW(T) Regulatory approvals received. Not under constructionSep 2028EIA-860M planned generators, file 2026-07
Utah Solar 1
ECG Utah Solar1, LLC
Solar Photovoltaic300 MW(P) Planned for installation, but regulatory approvals not initiatedDec 2027EIA-860M planned generators, file 2026-07
Gale 1 Solar
33UI 8me LLC
Solar Photovoltaic300 MW(P) Planned for installation, but regulatory approvals not initiatedAug 2030EIA-860M planned generators, file 2026-07
Intermountain Pumped Storage Project
Premium Energy Holdings
Hydroelectric Pumped Storage1000 MW(P) Planned for installation, but regulatory approvals not initiatedJul 2028EIA-860M planned generators, file 2026-07
Gale 1 Solar
33UI 8me LLC
Batteries150 MW(P) Planned for installation, but regulatory approvals not initiatedAug 2030EIA-860M planned generators, file 2026-07
Want the list for one address? The full report measures distance from a street address to each mapped planned project. Get the Planned Power Project Report for $12.

Sources

Neither dataset records data centres or other electricity demand. Projects that are small, unreported or filed after the published dates do not appear.

QueueLedger reports public EIA and Lawrence Berkeley National Laboratory records of planned generators and interconnection requests near an address. It is not a utility, a developer, a regulator, an appraiser or a legal advisor, and a report says nothing about whether any project will be approved, built or cancelled.