Planned power projects in Ward, TX
3 planned generator projects are listed for Ward County, TX in the EIA-860M inventory, with a combined stated nameplate of 2334.9 MW. By type: Gas or other fossil 3.
Planned generators (EIA-860M)
| Project | Type | Capacity | Status (as reported) | Planned online | Source |
|---|---|---|---|---|---|
| CPV Basin Ranch Energy Center CPV Basin Ranch | Natural Gas Fired Combined Cycle | 1445 MW | (U) Under construction, less than or equal to 50 percent complete | Feb 2029 | EIA-860M planned generators, file 2026-07 |
| Vast Sands Power Permian Power I LLC | Natural Gas Fired Combustion Turbine | 880 MW | (U) Under construction, less than or equal to 50 percent complete | May 2027 | EIA-860M planned generators, file 2026-07 |
| Staghorn Gas RPC Merchant, LLC | Natural Gas Internal Combustion Engine | 9.9 MW | (V) Under construction, more than 50 percent complete | Oct 2026 | EIA-860M planned generators, file 2026-07 |
Want the list for one address? The full report measures distance from a street address to each mapped planned project. Get the Planned Power Project Report for $12.
Sources
- EIA-860M monthly generator inventory: https://www.eia.gov/electricity/data/eia860m/
- LBNL Queued Up interconnection queue data: https://emp.lbl.gov/queues
Neither dataset records data centres or other electricity demand. Projects that are small, unreported or filed after the published dates do not appear.
QueueLedger reports public EIA and Lawrence Berkeley National Laboratory records of planned generators and interconnection requests near an address. It is not a utility, a developer, a regulator, an appraiser or a legal advisor, and a report says nothing about whether any project will be approved, built or cancelled.