Planned power projects in Navarro, TX

11 planned generator projects are listed for Navarro County, TX in the EIA-860M inventory, with a combined stated nameplate of 2231.1 MW. By type: Solar 7 · Battery storage 2 · Wind 2.

Planned generators (EIA-860M)

ProjectTypeCapacityStatus (as reported)Planned onlineSource
Tehuacana Creek Solar
Parliament Energy Holdings LLC
Solar Photovoltaic644.8 MW(V) Under construction, more than 50 percent completeMay 2027EIA-860M planned generators, file 2026-07
Tehuacana Creek Solar
Parliament Energy Holdings LLC
Batteries418 MW(V) Under construction, more than 50 percent completeDec 2026EIA-860M planned generators, file 2026-07
Yellow Cat Wind, LLC
RWE Clean Energy
Onshore Wind Turbine270 MW(V) Under construction, more than 50 percent completeDec 2026EIA-860M planned generators, file 2026-07
Armadillo Solar Center
AES Clean Energy
Solar Photovoltaic175 MW(U) Under construction, less than or equal to 50 percent completeApr 2027EIA-860M planned generators, file 2026-07
Bluebonnet Prairie Wind
Leeward Asset Management, LLC
Onshore Wind Turbine170 MW(U) Under construction, less than or equal to 50 percent completeDec 2027EIA-860M planned generators, file 2026-07
Wensowitch Solar Park
Greenalia Solar Power Wensowitch, LLC
Solar Photovoltaic145.6 MW(T) Regulatory approvals received. Not under constructionNov 2028EIA-860M planned generators, file 2026-07
Elm Flats Solar
Birch Creek Development
Solar Photovoltaic125 MW(U) Under construction, less than or equal to 50 percent completeSep 2026EIA-860M planned generators, file 2026-07
Main Horn Solar
Main Horn Solar LLC
Solar Photovoltaic100 MW(P) Planned for installation, but regulatory approvals not initiatedDec 2029EIA-860M planned generators, file 2026-07
Eytcheson Solar
Gransolar Texas Fourteen, LLC
Solar Photovoltaic76.4 MW(P) Planned for installation, but regulatory approvals not initiatedJan 2028EIA-860M planned generators, file 2026-07
Whistle Solar
Gransolar Texas Nineteen LLC
Solar Photovoltaic56.3 MW(L) Regulatory approvals pending. Not under constructionMay 2028EIA-860M planned generators, file 2026-07
Elm Flats Solar
Birch Creek Development
Batteries50 MW(U) Under construction, less than or equal to 50 percent completeSep 2026EIA-860M planned generators, file 2026-07
Want the list for one address? The full report measures distance from a street address to each mapped planned project. Get the Planned Power Project Report for $12.

Sources

Neither dataset records data centres or other electricity demand. Projects that are small, unreported or filed after the published dates do not appear.

QueueLedger reports public EIA and Lawrence Berkeley National Laboratory records of planned generators and interconnection requests near an address. It is not a utility, a developer, a regulator, an appraiser or a legal advisor, and a report says nothing about whether any project will be approved, built or cancelled.