6 planned generator projects are listed for Jones County, TX in the EIA-860M inventory, with a combined stated nameplate of 1418.5 MW. By type: Solar 5 ยท Battery storage 1.

Planned generators (EIA-860M)

ProjectTypeCapacityStatus (as reported)Planned onlineSource
Funston Solar
Funston Solar, LLC
Solar Photovoltaic350 MW(V) Under construction, more than 50 percent completeDec 2026EIA-860M planned generators, file 2026-07
Tiger Solar
Vaca Del Sol, LLC
Solar Photovoltaic250 MW(V) Under construction, more than 50 percent completeDec 2026EIA-860M planned generators, file 2026-07
Anson 2 Solar
Anson Solar Center 2, LLC
Solar Photovoltaic218.5 MW(V) Under construction, more than 50 percent completeSep 2026EIA-860M planned generators, file 2026-07
Jones City 1 Solar
Lightsource Renewable Energy Asset Management, LLC
Solar Photovoltaic215 MW(TS) Construction complete, but not yet in commercial operationOct 2026EIA-860M planned generators, file 2026-07
Jones City 2 Solar
Lightsource Renewable Energy Asset Management, LLC
Batteries200 MW(U) Under construction, less than or equal to 50 percent completeMar 2027EIA-860M planned generators, file 2026-07
Jones City 2 Solar
Lightsource Renewable Energy Asset Management, LLC
Solar Photovoltaic185 MW(V) Under construction, more than 50 percent completeOct 2026EIA-860M planned generators, file 2026-07
Want the list for one address? The full report measures distance from a street address to each mapped planned project. Get the Planned Power Project Report for $12.

Sources

Neither dataset records data centres or other electricity demand. Projects that are small, unreported or filed after the published dates do not appear.

QueueLedger reports public EIA and Lawrence Berkeley National Laboratory records of planned generators and interconnection requests near an address. It is not a utility, a developer, a regulator, an appraiser or a legal advisor, and a report says nothing about whether any project will be approved, built or cancelled.