Groundwork Register
EIA-860M file 2026-07
Planned power projects in Hill, TX
12 planned generator projects are listed for Hill County, TX in the EIA-860M inventory, with a combined stated nameplate of 2124 MW. By type: Solar 8 · Battery storage 3 · Wind 1.
Planned generators (EIA-860M)
| Project | Type | Capacity | Status (as reported) | Planned online | Source |
|---|---|---|---|---|---|
| Hill Solar 1 Hill Solar 1, LLC | Solar Photovoltaic | 405 MW | (TS) Construction complete, but not yet in commercial operation | Aug 2026 | EIA-860M planned generators, file 2026-07 |
| Ash Creek BESS ACTX BESS Project LLC | Batteries | 306 MW | (P) Planned for installation, but regulatory approvals not initiated | Mar 2028 | EIA-860M planned generators, file 2026-07 |
| Hubbard Wind II Hubbard Wind II, LLC | Onshore Wind Turbine | 304.5 MW | (V) Under construction, more than 50 percent complete | Sep 2026 | EIA-860M planned generators, file 2026-07 |
| Hill Solar II Hill Solar II, LLC | Solar Photovoltaic | 200 MW | (TS) Construction complete, but not yet in commercial operation | Aug 2026 | EIA-860M planned generators, file 2026-07 |
| OCI Hillsboro HEC Renewable Energy America LLC | Solar Photovoltaic | 200 MW | (P) Planned for installation, but regulatory approvals not initiated | Oct 2027 | EIA-860M planned generators, file 2026-07 |
| OCI Hillsboro HEC Renewable Energy America LLC | Batteries | 200 MW | (P) Planned for installation, but regulatory approvals not initiated | Dec 2027 | EIA-860M planned generators, file 2026-07 |
| Vial BESS Gransolar Texas Eleven LLC | Batteries | 141.4 MW | (L) Regulatory approvals pending. Not under construction | Sep 2027 | EIA-860M planned generators, file 2026-07 |
| Three W Solar Three W Solar LLC | Solar Photovoltaic | 110.9 MW | (TS) Construction complete, but not yet in commercial operation | Aug 2026 | EIA-860M planned generators, file 2026-07 |
| Leitrim Solar Park Greenalia Solar Power Leitrim, LLC | Solar Photovoltaic | 91.2 MW | (T) Regulatory approvals received. Not under construction | Oct 2030 | EIA-860M planned generators, file 2026-07 |
| Payne Battlecreek Solar Gransolar Texas Ten LLC | Solar Photovoltaic | 85 MW | (L) Regulatory approvals pending. Not under construction | Aug 2027 | EIA-860M planned generators, file 2026-07 |
| Edens Solar RIC Development, LLC | Solar Photovoltaic | 70 MW | (P) Planned for installation, but regulatory approvals not initiated | Sep 2028 | EIA-860M planned generators, file 2026-07 |
| Hillsboro Solar Project Ellomay USA Inc | Solar Photovoltaic | 10 MW | (V) Under construction, more than 50 percent complete | Sep 2026 | EIA-860M planned generators, file 2026-07 |
Want the list for one address? The full report measures distance from a street address to each mapped planned project. Get the Planned Power Project Report for $12.
Sources
- EIA-860M monthly generator inventory: https://www.eia.gov/electricity/data/eia860m/
- LBNL Queued Up interconnection queue data: https://emp.lbl.gov/queues
Neither dataset records data centres or other electricity demand. Projects that are small, unreported or filed after the published dates do not appear.
QueueLedger reports public EIA and Lawrence Berkeley National Laboratory records of planned generators and interconnection requests near an address. It is not a utility, a developer, a regulator, an appraiser or a legal advisor, and a report says nothing about whether any project will be approved, built or cancelled.