12 planned generator projects are listed for Brazoria County, TX in the EIA-860M inventory, with a combined stated nameplate of 2498.9 MW. By type: Battery storage 8 · Solar 3 · Wind 1.
Planned generators (EIA-860M)
| Project | Type | Capacity | Status (as reported) | Planned online | Source |
|---|---|---|---|---|---|
| Cottonwood Bayou Solar Cottonwood Bayou Solar, LLC | Solar Photovoltaic | 350 MW | (TS) Construction complete, but not yet in commercial operation | Aug 2026 | EIA-860M planned generators, file 2026-07 |
| Myrtle Solar, LLC Myrtle Solar, LLC | Solar Photovoltaic | 313 MW | (TS) Construction complete, but not yet in commercial operation | Sep 2026 | EIA-860M planned generators, file 2026-07 |
| Elio Energy LLC Elio Energy LLC | Batteries | 300 MW | (P) Planned for installation, but regulatory approvals not initiated | Dec 2027 | EIA-860M planned generators, file 2026-07 |
| Rock N' Roll Lydian Energy | Batteries | 250 MW | (L) Regulatory approvals pending. Not under construction | Oct 2027 | EIA-860M planned generators, file 2026-07 |
| Bell Creek BESS LLC Nexus Renewables U.S. Inc. | Batteries | 200.9 MW | (P) Planned for installation, but regulatory approvals not initiated | Nov 2028 | EIA-860M planned generators, file 2026-07 |
| Castor Engie North America | Batteries | 200 MW | (U) Under construction, less than or equal to 50 percent complete | Sep 2026 | EIA-860M planned generators, file 2026-07 |
| Willow Beach Wind AES Clean Energy | Onshore Wind Turbine | 200 MW | (L) Regulatory approvals pending. Not under construction | Feb 2029 | EIA-860M planned generators, file 2026-07 |
| Brazos River BESS LLC Nexus Renewables U.S. Inc. | Batteries | 180 MW | (P) Planned for installation, but regulatory approvals not initiated | Nov 2028 | EIA-860M planned generators, file 2026-07 |
| Bocanova Energy Storage II Bocanova Power II LLC | Batteries | 150 MW | (V) Under construction, more than 50 percent complete | Aug 2026 | EIA-860M planned generators, file 2026-07 |
| Brazoria Solar I Brazoria Solar i, LLC | Solar Photovoltaic | 250 MW | (TS) Construction complete, but not yet in commercial operation | Aug 2026 | EIA-860M planned generators, file 2026-07 |
| Bodkin BESS Bodkin BESS LLC | Batteries | 75 MW | (T) Regulatory approvals received. Not under construction | Dec 2028 | EIA-860M planned generators, file 2026-07 |
| Second Division Solar Lightsource Renewable Energy Asset Management, LLC | Batteries | 30 MW | (L) Regulatory approvals pending. Not under construction | Dec 2031 | EIA-860M planned generators, file 2026-07 |
Want the list for one address? The full report measures distance from a street address to each mapped planned project. Get the Planned Power Project Report for $12.
Sources
- EIA-860M monthly generator inventory: https://www.eia.gov/electricity/data/eia860m/
- LBNL Queued Up interconnection queue data: https://emp.lbl.gov/queues
Neither dataset records data centres or other electricity demand. Projects that are small, unreported or filed after the published dates do not appear.
QueueLedger reports public EIA and Lawrence Berkeley National Laboratory records of planned generators and interconnection requests near an address. It is not a utility, a developer, a regulator, an appraiser or a legal advisor, and a report says nothing about whether any project will be approved, built or cancelled.