Planned power projects in Clark, NV
17 planned generator projects are listed for Clark County, NV in the EIA-860M inventory, with a combined stated nameplate of 4230.5 MW. By type: Solar 9 ยท Battery storage 8.
Planned generators (EIA-860M)
| Project | Type | Capacity | Status (as reported) | Planned online | Source |
|---|---|---|---|---|---|
| Rough Hat Candela Renewables, LLC | Solar Photovoltaic | 400 MW | (L) Regulatory approvals pending. Not under construction | Dec 2027 | EIA-860M planned generators, file 2026-07 |
| Purple Sage Energy Center Noble Solar LLC | Batteries | 400 MW | (P) Planned for installation, but regulatory approvals not initiated | Nov 2028 | EIA-860M planned generators, file 2026-07 |
| Purple Sage Energy Center Noble Solar LLC | Solar Photovoltaic | 400 MW | (P) Planned for installation, but regulatory approvals not initiated | Nov 2028 | EIA-860M planned generators, file 2026-07 |
| Arida Solar (Hybrid) 326FW 8me LLC | Solar Photovoltaic | 370 MW | (P) Planned for installation, but regulatory approvals not initiated | Jun 2029 | EIA-860M planned generators, file 2026-07 |
| Arida Solar (Hybrid) 326FW 8me LLC | Batteries | 370 MW | (P) Planned for installation, but regulatory approvals not initiated | Jun 2029 | EIA-860M planned generators, file 2026-07 |
| Bonanza Solar and Storage Project EDF Renewables Development, Inc. | Solar Photovoltaic | 300 MW | (L) Regulatory approvals pending. Not under construction | Dec 2027 | EIA-860M planned generators, file 2026-07 |
| Vitex Storage Cypress Creek Renewables | Batteries | 300 MW | (L) Regulatory approvals pending. Not under construction | Jun 2028 | EIA-860M planned generators, file 2026-07 |
| Southern Bighorn Solar Hybrid 300MS 8me LLC | Batteries | 300 MW | (P) Planned for installation, but regulatory approvals not initiated | Jul 2028 | EIA-860M planned generators, file 2026-07 |
| Southern Bighorn Solar Hybrid 300MS 8me LLC | Solar Photovoltaic | 300 MW | (P) Planned for installation, but regulatory approvals not initiated | Jul 2028 | EIA-860M planned generators, file 2026-07 |
| Dry Lake East Energy Center Dry Lake East Energy Center | Solar Photovoltaic | 200 MW | (V) Under construction, more than 50 percent complete | Dec 2026 | EIA-860M planned generators, file 2026-07 |
| Bonanza Solar and Storage Project EDF Renewables Development, Inc. | Batteries | 195 MW | (L) Regulatory approvals pending. Not under construction | Dec 2027 | EIA-860M planned generators, file 2026-07 |
| Boulder Solar III LLC 174 Power Global Corp. | Solar Photovoltaic | 128 MW | (P) Planned for installation, but regulatory approvals not initiated | Jun 2027 | EIA-860M planned generators, file 2026-07 |
| Boulder Solar III LLC 174 Power Global Corp. | Batteries | 128 MW | (P) Planned for installation, but regulatory approvals not initiated | Jun 2027 | EIA-860M planned generators, file 2026-07 |
| Roccasecca BESS LLC Roccasecca BESS LLC | Batteries | 126.5 MW | (V) Under construction, more than 50 percent complete | Feb 2027 | EIA-860M planned generators, file 2026-07 |
| Boulder Flats Solar Boulder Flats Solar, LLC | Solar Photovoltaic | 113 MW | (V) Under construction, more than 50 percent complete | Dec 2028 | EIA-860M planned generators, file 2026-07 |
| Southern Bighorn Solar 2 425LM 8ME LLC | Solar Photovoltaic | 100 MW | (L) Regulatory approvals pending. Not under construction | Jul 2028 | EIA-860M planned generators, file 2026-07 |
| Southern Bighorn Solar 2 425LM 8ME LLC | Batteries | 100 MW | (L) Regulatory approvals pending. Not under construction | Jul 2028 | EIA-860M planned generators, file 2026-07 |
Want the list for one address? The full report measures distance from a street address to each mapped planned project. Get the Planned Power Project Report for $12.
Sources
- EIA-860M monthly generator inventory: https://www.eia.gov/electricity/data/eia860m/
- LBNL Queued Up interconnection queue data: https://emp.lbl.gov/queues
Neither dataset records data centres or other electricity demand. Projects that are small, unreported or filed after the published dates do not appear.
QueueLedger reports public EIA and Lawrence Berkeley National Laboratory records of planned generators and interconnection requests near an address. It is not a utility, a developer, a regulator, an appraiser or a legal advisor, and a report says nothing about whether any project will be approved, built or cancelled.