Groundwork Register
EIA-860M file 2026-07

Planned power projects in San Bernardino, CA

18 planned generator projects are listed for San Bernardino County, CA in the EIA-860M inventory, with a combined stated nameplate of 1499.5 MW. By type: Battery storage 9 · Solar 7 · Other 1 · Gas or other fossil 1.

Planned generators (EIA-860M)

ProjectTypeCapacityStatus (as reported)Planned onlineSource
Roadhouse Energy Center
Roadhouse Energy Storage
Batteries300 MW(L) Regulatory approvals pending. Not under constructionDec 2027EIA-860M planned generators, file 2026-07
Sienna Solar Farm
99MT 8me, LLC
Solar Photovoltaic200 MW(P) Planned for installation, but regulatory approvals not initiatedDec 2028EIA-860M planned generators, file 2026-07
Sienna Solar Farm
99MT 8me, LLC
Batteries200 MW(P) Planned for installation, but regulatory approvals not initiatedDec 2028EIA-860M planned generators, file 2026-07
Vidal Energy Center
CDH Vidal LLC
Batteries160 MW(V) Under construction, more than 50 percent completeDec 2026EIA-860M planned generators, file 2026-07
Vidal Energy Center
CDH Vidal LLC
Solar Photovoltaic160 MW(V) Under construction, more than 50 percent completeDec 2026EIA-860M planned generators, file 2026-07
Overnight Solar
Overnight Solar LLC
Batteries150 MW(V) Under construction, more than 50 percent completeJan 2027EIA-860M planned generators, file 2026-07
Overnight Solar
Overnight Solar LLC
Solar Photovoltaic150 MW(U) Under construction, less than or equal to 50 percent completeJan 2027EIA-860M planned generators, file 2026-07
Sienna 2 Solar and Storage Project
44ST 8ME LLC
Solar Photovoltaic55 MW(P) Planned for installation, but regulatory approvals not initiatedMar 2029EIA-860M planned generators, file 2026-07
Sienna 2 Solar and Storage Project
44ST 8ME LLC
Batteries55 MW(P) Planned for installation, but regulatory approvals not initiatedMar 2029EIA-860M planned generators, file 2026-07
Baldy Mesa Storage
AES Clean Energy
Batteries50 MW(V) Under construction, more than 50 percent completeSep 2026EIA-860M planned generators, file 2026-07
Bear Valley Battery Plant
Bear Valley Electric Service
Batteries5 MW(P) Planned for installation, but regulatory approvals not initiatedApr 2027EIA-860M planned generators, file 2026-07
Minneola Solar
Minneola Solar
Solar Photovoltaic3 MW(U) Under construction, less than or equal to 50 percent completeSep 2026EIA-860M planned generators, file 2026-07
Redlands DC 9 - sline609
Prologis Logistics Services Incorporated
Solar Photovoltaic2.6 MW(U) Under construction, less than or equal to 50 percent completeSep 2026EIA-860M planned generators, file 2026-07
Redlands DC 9 - sline609
Prologis Logistics Services Incorporated
Batteries2.4 MW(U) Under construction, less than or equal to 50 percent completeOct 2026EIA-860M planned generators, file 2026-07
CA Bloomington 2551 S Lilac Avenue Micro
Catalyze Bloomington 2551 S Lilac Avenue Microgrid LLC
Solar Photovoltaic1.5 MW(V) Under construction, more than 50 percent completeNov 2026EIA-860M planned generators, file 2026-07
CA Bloomington 2551 S Lilac Avenue Micro
Catalyze Bloomington 2551 S Lilac Avenue Microgrid LLC
Batteries1.5 MW(V) Under construction, more than 50 percent completeNov 2026EIA-860M planned generators, file 2026-07
OES Biogas Power
Organic Energy Solutions, Inc.
Other Waste Biomass2.6 MW(TS) Construction complete, but not yet in commercial operationNov 2026EIA-860M planned generators, file 2026-07
Energy Center
University of Redlands
Natural Gas Fired Combustion Turbine0.9 MW(P) Planned for installation, but regulatory approvals not initiatedDec 2030EIA-860M planned generators, file 2026-07
Want the list for one address? The full report measures distance from a street address to each mapped planned project. Get the Planned Power Project Report for $12.

Sources

Neither dataset records data centres or other electricity demand. Projects that are small, unreported or filed after the published dates do not appear.

QueueLedger reports public EIA and Lawrence Berkeley National Laboratory records of planned generators and interconnection requests near an address. It is not a utility, a developer, a regulator, an appraiser or a legal advisor, and a report says nothing about whether any project will be approved, built or cancelled.