Groundwork Register
EIA-860M file 2026-07

Planned power projects in Kern, CA

29 planned generator projects are listed for Kern County, CA in the EIA-860M inventory, with a combined stated nameplate of 3418.5 MW. By type: Solar 17 ยท Battery storage 12.

Planned generators (EIA-860M)

ProjectTypeCapacityStatus (as reported)Planned onlineSource
Bellefield 2 Solar & Energy Storage Farm
26SB 8me LLC
Solar Photovoltaic500 MW(V) Under construction, more than 50 percent completeSep 2026EIA-860M planned generators, file 2026-07
Bellefield 2 Solar & Energy Storage Farm
26SB 8me LLC
Batteries500 MW(V) Under construction, more than 50 percent completeNov 2026EIA-860M planned generators, file 2026-07
Pelicans Jaw Hybrid Solar
Pelicans Jaw Solar LLC
Solar Photovoltaic440 MW(TS) Construction complete, but not yet in commercial operationApr 2027EIA-860M planned generators, file 2026-07
Pelicans Jaw Hybrid Solar
Pelicans Jaw Solar LLC
Batteries238.5 MW(TS) Construction complete, but not yet in commercial operationApr 2027EIA-860M planned generators, file 2026-07
Sanborn Hybrid 3
Terra-Gen Operating Co-Hybrid
Batteries210 MW(U) Under construction, less than or equal to 50 percent completeNov 2026EIA-860M planned generators, file 2026-07
Sanborn Hybrid 3
Terra-Gen Operating Co-Hybrid
Solar Photovoltaic368 MW(U) Under construction, less than or equal to 50 percent completeNov 2026EIA-860M planned generators, file 2026-07
Aratina Solar Center 2
45MG 8me LLC
Solar Photovoltaic150 MW(V) Under construction, more than 50 percent completeDec 2026EIA-860M planned generators, file 2026-07
Bellefield 3 Solar and Battery Storage
51LV 8me, LLC
Solar Photovoltaic150 MW(P) Planned for installation, but regulatory approvals not initiatedMay 2030EIA-860M planned generators, file 2026-07
Bellefield 3 Solar and Battery Storage
51LV 8me, LLC
Batteries150 MW(P) Planned for installation, but regulatory approvals not initiatedMay 2030EIA-860M planned generators, file 2026-07
Aratina Solar Center 2
45MG 8me LLC
Batteries113 MW(V) Under construction, more than 50 percent completeDec 2026EIA-860M planned generators, file 2026-07
Rosamond South II
Golden Fields Solar VI, LLC
Batteries140 MW(V) Under construction, more than 50 percent completeNov 2026EIA-860M planned generators, file 2026-07
Jasmine
AES Clean Energy
Solar Photovoltaic70 MW(V) Under construction, more than 50 percent completeMay 2027EIA-860M planned generators, file 2026-07
Chalan
Origis Energy USA, Inc
Solar Photovoltaic64.9 MW(V) Under construction, more than 50 percent completeSep 2026EIA-860M planned generators, file 2026-07
Jasmine
AES Clean Energy
Batteries64.4 MW(V) Under construction, more than 50 percent completeMay 2027EIA-860M planned generators, file 2026-07
Syracuse and Tours Renewable Energy
Vesper Energy Development LLC
Batteries40 MW(T) Regulatory approvals received. Not under constructionNov 2027EIA-860M planned generators, file 2026-07
Syracuse and Tours Renewable Energy
Vesper Energy Development LLC
Solar Photovoltaic40 MW(T) Regulatory approvals received. Not under constructionNov 2027EIA-860M planned generators, file 2026-07
Windhub Solar B, LLC
Windhub Solar B, LLC
Solar Photovoltaic26.4 MW(V) Under construction, more than 50 percent completeOct 2026EIA-860M planned generators, file 2026-07
Chalan
Origis Energy USA, Inc
Batteries25 MW(V) Under construction, more than 50 percent completeSep 2026EIA-860M planned generators, file 2026-07
Solar Star 3
Solar Star 3, LLC
Solar Photovoltaic24 MW(V) Under construction, more than 50 percent completeOct 2026EIA-860M planned generators, file 2026-07
Solar Star 4
Solar Star 4, LLC
Solar Photovoltaic24 MW(V) Under construction, more than 50 percent completeOct 2026EIA-860M planned generators, file 2026-07
Solar Star 3
Solar Star 3, LLC
Batteries23 MW(V) Under construction, more than 50 percent completeOct 2026EIA-860M planned generators, file 2026-07
Solar Star 4
Solar Star 4, LLC
Batteries23 MW(V) Under construction, more than 50 percent completeOct 2026EIA-860M planned generators, file 2026-07
Gaskell West Storage 1, LLC
Matrix Renewables
Batteries21.6 MW(V) Under construction, more than 50 percent completeSep 2026EIA-860M planned generators, file 2026-07
Pistachio Road 1726-WD
Russell Pacific LLC
Solar Photovoltaic4.8 MW(V) Under construction, more than 50 percent completeSep 2026EIA-860M planned generators, file 2026-07
Ranch 4701
Wonderful Renewable Energy, LLC.
Solar Photovoltaic2.3 MW(V) Under construction, more than 50 percent completeSep 2026EIA-860M planned generators, file 2026-07

Showing the largest 25 of 29.

Want the list for one address? The full report measures distance from a street address to each mapped planned project. Get the Planned Power Project Report for $12.

Sources

Neither dataset records data centres or other electricity demand. Projects that are small, unreported or filed after the published dates do not appear.

QueueLedger reports public EIA and Lawrence Berkeley National Laboratory records of planned generators and interconnection requests near an address. It is not a utility, a developer, a regulator, an appraiser or a legal advisor, and a report says nothing about whether any project will be approved, built or cancelled.