Planned power projects in Pinal, AZ
10 planned generator projects are listed for Pinal County, AZ in the EIA-860M inventory, with a combined stated nameplate of 2272 MW. By type: Battery storage 5 · Solar 4 · Gas or other fossil 1.
Planned generators (EIA-860M)
| Project | Type | Capacity | Status (as reported) | Planned online | Source |
|---|---|---|---|---|---|
| Valley Farms Energy Center Valley Farms Energy Center, LLC | Batteries | 400 MW | (U) Under construction, less than or equal to 50 percent complete | Dec 2027 | EIA-860M planned generators, file 2026-07 |
| THREE SISTERS Solar Generation and BESS THSI bn, LLC | Batteries | 300 MW | (L) Regulatory approvals pending. Not under construction | Apr 2029 | EIA-860M planned generators, file 2026-07 |
| THREE SISTERS Solar Generation and BESS THSI bn, LLC | Solar Photovoltaic | 300 MW | (L) Regulatory approvals pending. Not under construction | Apr 2029 | EIA-860M planned generators, file 2026-07 |
| Sawtooth Solar EDF Renewables Development, Inc. | Batteries | 250 MW | (L) Regulatory approvals pending. Not under construction | Jun 2028 | EIA-860M planned generators, file 2026-07 |
| Sawtooth Solar EDF Renewables Development, Inc. | Solar Photovoltaic | 250 MW | (L) Regulatory approvals pending. Not under construction | Jun 2028 | EIA-860M planned generators, file 2026-07 |
| Selma Energy Center Selma Energy Center, LLC | Batteries | 150 MW | (U) Under construction, less than or equal to 50 percent complete | Dec 2027 | EIA-860M planned generators, file 2026-07 |
| Selma Energy Center Selma Energy Center, LLC | Solar Photovoltaic | 125 MW | (U) Under construction, less than or equal to 50 percent complete | Dec 2027 | EIA-860M planned generators, file 2026-07 |
| Kitt Solar 301AK 8me LLC | Batteries | 100 MW | (V) Under construction, more than 50 percent complete | Dec 2026 | EIA-860M planned generators, file 2026-07 |
| Kitt Solar 301AK 8me LLC | Solar Photovoltaic | 100 MW | (V) Under construction, more than 50 percent complete | Dec 2026 | EIA-860M planned generators, file 2026-07 |
| Coolidge Generation Station Salt River Project | Natural Gas Fired Combustion Turbine | 297 MW | (U) Under construction, less than or equal to 50 percent complete | Jul 2027 | EIA-860M planned generators, file 2026-07 |
Want the list for one address? The full report measures distance from a street address to each mapped planned project. Get the Planned Power Project Report for $12.
Sources
- EIA-860M monthly generator inventory: https://www.eia.gov/electricity/data/eia860m/
- LBNL Queued Up interconnection queue data: https://emp.lbl.gov/queues
Neither dataset records data centres or other electricity demand. Projects that are small, unreported or filed after the published dates do not appear.
QueueLedger reports public EIA and Lawrence Berkeley National Laboratory records of planned generators and interconnection requests near an address. It is not a utility, a developer, a regulator, an appraiser or a legal advisor, and a report says nothing about whether any project will be approved, built or cancelled.