6 planned generator projects are listed for Navajo County, AZ in the EIA-860M inventory, with a combined stated nameplate of 1900 MW. By type: Solar 3 ยท Battery storage 3.

Planned generators (EIA-860M)

ProjectTypeCapacityStatus (as reported)Planned onlineSource
Snowflake A Solar and BESS
Clenera DevCo LLC
Solar Photovoltaic475 MW(L) Regulatory approvals pending. Not under constructionAug 2027EIA-860M planned generators, file 2026-07
Snowflake A Solar and BESS
Clenera DevCo LLC
Batteries475 MW(L) Regulatory approvals pending. Not under constructionAug 2027EIA-860M planned generators, file 2026-07
Hashknife Energy Center LLC
Invenergy Services LLC
Solar Photovoltaic275 MW(V) Under construction, more than 50 percent completeSep 2026EIA-860M planned generators, file 2026-07
Hashknife Energy Center LLC
Invenergy Services LLC
Batteries275 MW(V) Under construction, more than 50 percent completeSep 2026EIA-860M planned generators, file 2026-07
Hashknife Energy Center II LLC
Invenergy Services LLC
Solar Photovoltaic200 MW(V) Under construction, more than 50 percent completeMar 2027EIA-860M planned generators, file 2026-07
Hashknife Energy Center II LLC
Invenergy Services LLC
Batteries200 MW(V) Under construction, more than 50 percent completeMar 2027EIA-860M planned generators, file 2026-07
Want the list for one address? The full report measures distance from a street address to each mapped planned project. Get the Planned Power Project Report for $12.

Sources

Neither dataset records data centres or other electricity demand. Projects that are small, unreported or filed after the published dates do not appear.

QueueLedger reports public EIA and Lawrence Berkeley National Laboratory records of planned generators and interconnection requests near an address. It is not a utility, a developer, a regulator, an appraiser or a legal advisor, and a report says nothing about whether any project will be approved, built or cancelled.