Planned power projects in Maricopa, AZ

11 planned generator projects are listed for Maricopa County, AZ in the EIA-860M inventory, with a combined stated nameplate of 3792 MW. By type: Battery storage 8 · Gas or other fossil 2 · Solar 1.

Planned generators (EIA-860M)

ProjectTypeCapacityStatus (as reported)Planned onlineSource
Maricopa Solar
Maricopa Solar
Batteries550 MW(U) Under construction, less than or equal to 50 percent completeSep 2026EIA-860M planned generators, file 2026-07
Saddleback Generation Station
Copia Power
Natural Gas Fired Combined Cycle1250 MW(P) Planned for installation, but regulatory approvals not initiatedDec 2030EIA-860M planned generators, file 2026-07
Desert Sand BESS
DESA bn, LLC
Batteries300 MW(L) Regulatory approvals pending. Not under constructionDec 2028EIA-860M planned generators, file 2026-07
Desert Sand BESS
DESA bn, LLC
Solar Photovoltaic300 MW(L) Regulatory approvals pending. Not under constructionDec 2028EIA-860M planned generators, file 2026-07
Romero Energy Center
Romero Energy Center, LLC
Batteries225 MW(U) Under construction, less than or equal to 50 percent completeJun 2027EIA-860M planned generators, file 2026-07
Romero Energy Center II, LLC
Romero Energy Center II, LLC
Batteries225 MW(U) Under construction, less than or equal to 50 percent completeJun 2028EIA-860M planned generators, file 2026-07
Desert Bloom
RE Desert Bloom LLC
Batteries150 MW(TS) Construction complete, but not yet in commercial operationAug 2026EIA-860M planned generators, file 2026-07
Agave
Arizona Public Service Co
Batteries150 MW(TS) Construction complete, but not yet in commercial operationSep 2026EIA-860M planned generators, file 2026-07
Sierra Luna Energy Storage
Sierra Luna Energy Storage LLC
Batteries150 MW(P) Planned for installation, but regulatory approvals not initiatedDec 2030EIA-860M planned generators, file 2026-07
White Tank Energy Storage
White Tank Energy Storage LLC
Batteries100 MW(U) Under construction, less than or equal to 50 percent completeMar 2027EIA-860M planned generators, file 2026-07
Red Hawk
Arizona Public Service Co
Natural Gas Fired Combustion Turbine392 MW(U) Under construction, less than or equal to 50 percent completeOct 2027EIA-860M planned generators, file 2026-07
Want the list for one address? The full report measures distance from a street address to each mapped planned project. Get the Planned Power Project Report for $12.

Sources

Neither dataset records data centres or other electricity demand. Projects that are small, unreported or filed after the published dates do not appear.

QueueLedger reports public EIA and Lawrence Berkeley National Laboratory records of planned generators and interconnection requests near an address. It is not a utility, a developer, a regulator, an appraiser or a legal advisor, and a report says nothing about whether any project will be approved, built or cancelled.