Planned power projects in La Paz, AZ

14 planned generator projects are listed for La Paz County, AZ in the EIA-860M inventory, with a combined stated nameplate of 3013.1 MW. By type: Solar 8 · Battery storage 5 · Solar plus storage 1.

Planned generators (EIA-860M)

ProjectTypeCapacityStatus (as reported)Planned onlineSource
Eagle Eye Solar and Storage
EAGL bn, LLC
Solar Photovoltaic400 MW(L) Regulatory approvals pending. Not under constructionMay 2028EIA-860M planned generators, file 2026-07
Eagle Eye Solar and Storage
EAGL bn, LLC
Batteries400 MW(L) Regulatory approvals pending. Not under constructionMay 2028EIA-860M planned generators, file 2026-07
Atlas
174 Power Global Corp.
Solar Photovoltaic300 MW(V) Under construction, more than 50 percent completeAug 2026EIA-860M planned generators, file 2026-07
ATLAS SOLAR IV
ATLAS SOLAR IV, LLC
Solar Photovoltaic300 MW(V) Under construction, more than 50 percent completeMar 2027EIA-860M planned generators, file 2026-07
ATLAS Solar X, LLC
ATLAS Solar Manager, LLC
Solar Photovoltaic225 MW(P) Planned for installation, but regulatory approvals not initiatedDec 2027EIA-860M planned generators, file 2026-07
Atlas VIII
Atlas VIII LLC
Batteries210 MW(V) Under construction, more than 50 percent completeSep 2026EIA-860M planned generators, file 2026-07
ATLAS Solar XI, LLC
ATLAS Solar Manager, LLC
Solar Photovoltaic200 MW(P) Planned for installation, but regulatory approvals not initiatedDec 2027EIA-860M planned generators, file 2026-07
La Paz Solar Tower
Enviromission, Inc
Solar Thermal without Energy Storage200 MW(P) Planned for installation, but regulatory approvals not initiatedJun 2030EIA-860M planned generators, file 2026-07
Atlas VIII
Atlas VIII LLC
Batteries172.4 MW(V) Under construction, more than 50 percent completeNov 2026EIA-860M planned generators, file 2026-07
Centennial Flats
Copia Power
Solar Photovoltaic166.7 MW(U) Under construction, less than or equal to 50 percent completeSep 2026EIA-860M planned generators, file 2026-07
Atlas BESS IV LLC
ATLAS BESS IV, LLC
Batteries150 MW(V) Under construction, more than 50 percent completeMar 2027EIA-860M planned generators, file 2026-07
ATLAS Solar VI, LLC
ATLAS Solar VI, LLC
Solar Photovoltaic100 MW(U) Under construction, less than or equal to 50 percent completeAug 2026EIA-860M planned generators, file 2026-07
ATLAS II
ATLAS Solar II, LLC
Solar Photovoltaic100 MW(V) Under construction, more than 50 percent completeNov 2026EIA-860M planned generators, file 2026-07
Centennial Flats
Copia Power
Batteries89 MW(U) Under construction, less than or equal to 50 percent completeSep 2026EIA-860M planned generators, file 2026-07
Want the list for one address? The full report measures distance from a street address to each mapped planned project. Get the Planned Power Project Report for $12.

Sources

Neither dataset records data centres or other electricity demand. Projects that are small, unreported or filed after the published dates do not appear.

QueueLedger reports public EIA and Lawrence Berkeley National Laboratory records of planned generators and interconnection requests near an address. It is not a utility, a developer, a regulator, an appraiser or a legal advisor, and a report says nothing about whether any project will be approved, built or cancelled.